Step 2 Install mounting ears.
Use a Phillips screwdriver to fix the mounting ears to both sides of the chassis with M4
screws, as shown in
Issue 03 (2017-12-15)
Figure 2-6 Installing floating nuts and guide rails
AC power frame
(AC power source is used)
Chassis
Figure
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
The second hole in rack unit 42 (for power)
The second hole in rack unit 41 (for power)
Location of floating nuts for guide rails
The second hole in rack unit 39 (for power)
The second hole in rack unit 38 (for power)
Location of floating nuts for guide rails
The second hole in rack unit 36 (for fiber spool)
The second hole in rack unit 35 (for fiber spool)
The first hole in rack unit 34 (for device)
The first hole in rack unit 31 (for device)
The third hole in rack unit 24 (for device)
The third hole in rack unit 21 (for device)
The first hole in rack unit 16 (for device)
The first hole in rack unit 13 (for device)
The third hole in rack unit 6 (for device)
The third hole in rack unit 3 (for device)
Location of floating nuts for guide rails
M6
1U
2-7.