DLP- D332 Install the TCC2/TCC2P Cards

Return to your originating procedure (NTP).
Step 4
DLP-D332 Install the TCC2/TCC2P Cards
Purpose
Tools/Equipment
Prerequisite Procedures None
Required/As Needed
Onsite/Remote
Security Level
When installing cards, allow each card to boot completely before installing the next card.
Note
Open the latches/ejectors of the TCC2/TCC2P card that you will install.
Step 1
Use the latches/ejectors to firmly slide the card along the guide rails until the card plugs into the
Step 2
receptacle at the back of the slot (Slot 7 or 11).
Verify that the card is inserted correctly and close the latches/ejectors on the card.
Step 3
Note
If you insert a card into a slot provisioned for a different card, all LEDs turn off.
Go to Step
Step 4
a.
Cisco ONS 15454 SDH Procedure Guide, R7.0
20-22
This task installs redundant TCC2/TCC2P cards. The first card you install
in the ONS 15454 SDH must be a TCC2/TCC2P card, and it must initialize
before you install any cross-connect or traffic cards.
Two TCC2/TCC2P cards
Required
Onsite
None
It is possible to close the latches/ejectors when the card is not completely plugged into the
backplane. Ensure that you cannot insert the card any further.
a
to verify the LED activity on the TCC2 card. For the TCC2P card, go to Step b.
For the TCC2 card:
All LEDs turn on briefly. The red FAIL LED and the yellow ACT/STBY LED turn on for about
15 seconds.
The red FAIL LED and the green ACT/STBY LED turn on for about 40 seconds.
The red FAIL LED blinks for about 15 seconds.
The red FAIL LED turns on for about 15 seconds. All LEDs turn on for about 3 seconds before
turning off for about 3 seconds.
Both green PWR LEDs turn on for 10 seconds. The PWR LEDs then turn red for 2 to 3 minutes
before going to steady green.
While the PWR LEDs are red for two to three minutes, the ACT/STBY, MJ, and MN LEDs turn
on, followed by the SNYC LED.
The boot up process is complete when the PWR LEDs turn green and the ACT/STBY remains
on. (The ACT/STBY LED will be green if this is the first TCC2 card installed, and amber if this
is the second TCC2 card installed.)