Turn Up a Node
If an E1000-2, E1000-2-G, G1000-4, G1K-4, ML1000-2, ML100X-8, or CE-1000-4 Ethernet card is
Step 8
installed, verify that it has a Gigabit Interface Converter (GBIC) or Small Form-factor Pluggable
(SFP/XFP) installed. If not, see the
Verify that STM-N cards (STM-1, STM-1-8, STM-4, STM-4-4, STM-16, STM-16 any slot (AS),
Step 9
STM-64, and MRC-12) are installed in the slots designated by your site plan. STM-1, STM-4, and
STM-16AS cards can be installed in Slots 1 to 6 or 12 to 17. The STM-1-8 and STM-4-4 can only be
installed in Slots 1 to 4 or 14 to 17, and the STM-16 and STM-64 can only be installed in Slots 5 to 6
and 12 to 13.
Note
Verify that all installed STM-N cards display a solid amber STBY LED.
Step 10
If transponder or muxponder cards are installed (TXP_MR_10G, TXP_MR_2.5G, TXPP_MR_2.5G,
Step 11
MXP_MR_2.5G, MXPP_MR_2.5G, MXP_2.5G_10G, TXP_MR_10E, TXP_MR_10E_L,
TXP_MR_10E_C, and MXP_2.5G_10E, MXP_2.5G_10E_C, MXP_2.5G_10E_L,
MXP_MR_10DME_L, or MXP_MR_10DME_C), verify that they are installed in Slots 1 to 6 or 12 to
17 and have GBIC or SFP connectors are installed. For information about installing and provisioning
TXP and MXP cards, refer to the Cisco ONS 15454 DWDM Procedure Guide.
If Fibre Channel (FC_MR-4) cards are installed, verify that the FC_MR-4 is installed in Slots 1 to 6 or
Step 12
12 to 17 and displays a solid green ACT (Active) LED.
Verify that fiber-optic cables are installed and connected to the locations indicated in the site plan. If the
Step 13
fiber-optic cables are not installed, complete the
procedure on page
Verify that fiber is routed correctly in the shelf assembly and fiber boots are installed properly. If the
Step 14
fiber is not routed on the shelf assembly, complete the
on page
page
17-35.
Verify that the software release shown on the LCD matches the software release indicated in your site
Step 15
plan. If the release does not match, perform one of the following procedures:
Perform a software upgrade using a Cisco ONS 15454 SDH software CD. Refer to the
release-specific software upgrade document for instructions.
Replace the TCC2/TCC2P cards with cards containing the correct release. Refer to the
Cisco ONS 15454 SDH Troubleshooting Guide.
Continue with the
Step 16
Stop. You have completed this procedure.
78-17194-01
The optics thresholds for the STM-64 and MRC-12 cards may not be set properly when they are
initially installed. As a result, some alarms associated with optical power may be generated soon
after the node is turned up. For this reason, the optics thresholds must be configured every time
the cards are installed or reset, or any time the TCC/TCC2 card is installed or reset. See
"DLP-D109 Change Optics Thresholds Settings for STM-64 and MRC-12 Cards" task on
page 18-12
for instructions on setting the optics thresholds.
2-16.
2-19. If the fiber boots are not installed, complete the
"NTP-D30 Create Users and Assign Security" procedure on page
"DLP-D335 Install GBIC or SFP/XFP Devices" task on page
"NTP-D19 Install Fiber-Optic Cables on Optical Cards"
"NTP-D245 Route Fiber-Optic Cables" procedure
Cisco ONS 15454 SDH Procedure Guide, R7.0
NTP- D24 Verify Card Installation
"DLP-D45 Install the Fiber Boot" task on
4-4.
20-28.
4-3

Advertisement

Table of Contents
loading

Table of Contents