NTP- D155 Convert a Point-to-Point or a Linear ADM to a Two-Fiber MS-SPRing Manually
NTP-D155 Convert a Point-to-Point or a Linear ADM to a
Two-Fiber MS-SPRing Manually
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Caution
This procedure is service affecting.
Note
Optical transmit and receive levels should be in their acceptable range as shown in
page
Step 1
Complete the
from a point-to-point or linear ADM to an MS-SPRing. If you are already logged in, continue with
Step 2.
According to local site practice, complete the
Step 2
page 15-5
Check for alarms and conditions. See the
Step 3
task on page 19-83
On the network map, right-click a span adjacent to the node you are logged into. A shortcut menu
Step 4
appears.
From the shortcut menu, click Circuits. The Circuits on Span window appears.
Step 5
Verify that the total number of active VC4 circuits does not exceed 50 percent of the span bandwidth. In
Step 6
the Circuits column, there is a block titled "Unused." This number should exceed 50 percent of the span
bandwidth.
Note
If the first half of the capacity is exceeded, this procedure cannot be completed. Bandwidth must be
Caution
50 percent unassigned to convert to an MS-SPRing. Refer to local procedures for relocating circuits if
these requirements are not met.
Cisco ONS 15454 SDH Procedure Guide, R7.0
13-8
This procedure upgrades a point-to-point configuration (two nodes) or a
linear ADM configuration (three or more nodes) to a two-fiber
MS-SPRing manually, that is, without using the in-service topology
upgrade wizard. Use this procedure if the wizard is unavailable or you
need to back out of the wizard.
None
NTP-D124 Provision a Point-to-Point Network, page 5-3
NTP-D38 Provision a Linear ADM Network, page 5-7
As needed
Onsite
Provisioning or higher
2-17.
"DLP-D60 Log into CTC" task on page 17-49
for each node in the configuration.
for instructions.
If the span is an STM-16, no more than 8 VC4s can be provisioned on the span. If the span is an
STM-64, no more than 32 VC4s can be provisioned on the span. If the span is an STM-4, no
more than 2 VC4s can be provisioned on the span.
Chapter 13
at one of the nodes that you want to convert
"NTP-D108 Back Up the Database" procedure on
"DLP-D298 Check the Network for Alarms and Conditions"
Convert Network Configurations
or
Table 2-4 on
78-17194-01

Advertisement

Table of Contents
loading

Table of Contents