9.4.1
Installing a GPGPU card
Field Replaceable Units (FRU)
Average hardware task duration: 10 minutes
Average hardware task duration including GPGPU power cable
installation: 40 minutes
9.4.1.1
Required tools
Preliminary and concluding steps: tool-less
●
Installing a GPGPU card
●
– Phillips PH2 / (+) No. 2 screw driver
– Flat nose pliers
9.4.1.2
Preliminary steps
Before installing an expansion card, perform the following steps:
Ê Disable BitLocker functionality as described in section
functionality" on page
Ê Disable boot watchdog functionality as described in section
SVOM boot watchdog functionality" on page
Ê Shut down the server as described in section
page
67.
Ê Remove the AC power cords from the PSU cable brackets and disconnect
them from the system as described in section
from the mains" on page
Ê When working on a rack-mounted server, extend it out of the rack as
described in section
If further required, remove the server from the rack as described in section
"Removing the server from the rack" on page
Ê Bring the server to its horizontal position.
TX300 S7 / RX350 S7
133.
68.
"Extending the server out of the rack" on page
Upgrade and Maintenance Manual
Expansion cards and backup units
"Disabling BitLocker
134.
"Shutting down the server" on
"Disconnecting the server
73.
"Disabling
72.