Post-Installation Checklist - Tekelec 1100 Hardware Manual

Application server
Hide thumbs Also See for 1100:
Table of Contents

Advertisement

Post Installation Procedures
2.
Apply the 145C cable tag to both ends of the logic ground cable. Also, apply
the "Do Not Disconnect" tag to both ends of the logic ground cable.
NOTE 1: DO NOT run Logic Ground or Power Cables on the cable horns
in the top middle of a frame.
NOTE 2: The number of inter-frame Logic Ground connections may vary
from the example shown in Figure 6-6.
3.
This procedure is complete.
Next, go to "How to Verify the Ground in an AC Environment" on page 6-13.
How to Verify the Ground in an AC Environment
Use the following procedure to o verify ground in an AC environment.
Procedure 6-7.
1.
Take the black lead of a VOM and insert it into the ground post on the AC
source plug/outlet being tested.
2.
Take the red lead of the VOM and insert it into one of the hot sides of the
plug/outlet. The meter should now read 208 VDC.
3.
While keeping the black lead in place, remove the red lead from the branch it
was inserted into in step 2 and insert it into the other branch of the
outlet/plug. Again the meter should read 208 VDC.
4.
This procedure is complete.

Post-Installation Checklist

After you have performed installation procedures in this manual, fill out the
checklist shown in Table 6-1.
910-2969-001 Revision H, February 2007
Preliminary
Verify AC ground
6-13

Advertisement

Table of Contents
loading