Tekelec 1100 Hardware Manual page 54

Application server
Hide thumbs Also See for 1100:
Table of Contents

Advertisement

3.
From each anchor remove all pieces above the metal sleeve. Retain the pieces
for use in step 7.
4.
Lay the isolator pad on the floor with the holes in the isolator pad aligned
over the anchor assemblies.
5.
Roll the frame (still on the dolly) into position above the isolator pad.
6.
Lower the frame onto the floor with the holes in the frame aligned over the
anchor assemblies. For instructions about how to lower the frame, refer to
822-0094-02.
7.
Install the three square washers, the round fiberglass washer, the large steel
washer, and the torque nut (with red plastic cover) in the order shown in
Figure 4-3. (The large steel washer, nylon shoulder washer, and round fiber
washer are found in the mounting hardware kit.)
When reassembling the anchor assembly, the bottom of the threaded rod must
be flush with the bottom of the cone nut and the torque nut must be near the
top of the threaded rod.
NOTE: When reassembling any anchor bolt assembly, lightly finger
tighten only.
4-8
Preliminary
910-2969-001 Revision H, February 2007
How to Install a T1100 AS Frame