Chapter 6. Post Installation Procedures; Introduction; How To Connect Frame Ground And Logic Ground - Tekelec 1100 Hardware Manual

Application server
Hide thumbs Also See for 1100:
Table of Contents

Advertisement

Introduction

This chapter describes the activities that should be performed after either of the
following types of installation:
• A heavy duty frame that contains T1100 AS hardware has been installed
• T1100 AS hardware has been installed in an existing frame
NOTE: Some of the figures in this section show the Tekelec T1000. The
T1000 is identical in size to the T1100, and the frame installation
instructions are the same for both chassis.

How to Connect Frame Ground and Logic Ground

The procedures in this section must be performed before turning on the power to
the frame. To ground a T1100 AS hardware system, the following tasks must be
performed:
• Prepare the ground cables (required only in a DC environment); see "How to
Prepare the Ground Cables" on page 6-4
• Ground the frame (required only in a DC environment); see "How to Ground
the Frame in a DC Environment" on page 6-4.
NOTE: Grounding for AC systems is provided through the AC electrical
circuit; however, the T1100 AS frame can be grounded with an isolated
frame ground. Customers are responsible for providing the connection
from the LSMS frame to the customer frame grounding point.
• Ground the chassis; see either of the following:
— "How to Connect T1100 AS Chassis Ground from T1100 AS Chassis to
Frame in DC Environment" on page 6-7
— "How to Verify the Ground in an AC Environment" on page 6-13
• Ground the logic for the T1100 AS unit; see "How to Ground the Logic
Connector in a DC Environment" on page 6-8 or "How to Ground the Logic
Connector in a AC Environment" on page 6-11.
• Verify the grounding; see one of the following:
— "How to Verify the Ground in a DC Environment" on page 6-11
— "How to Verify the Ground in an AC Environment" on page 6-13
DANGER: Strictly observe all grounding requirements to reduce the risk of
electric shock.
6-2
Preliminary
910-2969-001 Revision H, February 2007
Post Installation Procedures