How To Cable Components Added To Existing Frames; How To Cable A T1100 As Unit Added To An Existing Heavy Duty Frame; How To Cable A T1100 As Installed In Customer-Provided Frame - Tekelec 1100 Hardware Manual

Application server
Hide thumbs Also See for 1100:
Table of Contents

Advertisement

18.
You must perform the procedures in"Post Installation Procedures" on
page 6-1 before powering up the unit.
WARNING: Do not power up the unit at this time.
19.
Replace any plastic panels and doors that were removed.
20.
This procedure is complete.
Next, perform the procedures described in Chapter 6, "Post Installation
Procedures."

How to Cable Components Added to Existing Frames

To cable equipment added to an existing frame, follow the directions in one of the
following sections:
• "How to Cable a T1100 AS Unit Added to an Existing Heavy Duty Frame" on
page 5-14
• "How to Cable a T1100 AS Installed in Customer-Provided Frame" on
page 5-14
How to Cable a T1100 AS Unit Added to an Existing Heavy
Duty Frame
WARNING: Verify that all breakers are set to the OFF (O) position.
In a Direct Current (DC) environment, after an additional T1100 AS unit has been
installed, attach cables.
To determine the cables used and how to connect them, refer to the
diagram, which lists each cable, its quantity, length, how it is used, and a diagram
of how to connect it.
NOTE: Some of the listed cables are used only as required. Actual cables
used may vary by application.
How to Cable a T1100 AS Installed in
Customer-Provided Frame
WARNING: Verify that all breakers are set to the OFF (O) position, and that
all power distribution unit switches are in the OFF position.
5-14
How to Install Hardware in an Existing Frame
Preliminary
910-2969-001 Revision H, February 2007