Figure 4-7. Anchoring Frame To Raised Floor With Support Channel - Tekelec 1100 Hardware Manual

Application server
Hide thumbs Also See for 1100:
Table of Contents

Advertisement

How to Install a T1100 AS Frame

Figure 4-7. Anchoring Frame to Raised Floor with Support Channel

5 threads of the
threaded rod
must show above
the nut
Support channel
(example Unistrut)
4.
From inside the frame, drop onto each threaded rod the following
components in the order shown (see Figure 4-7):
a.
Metal sleeve inside a nylon shoulder washer
b.
Fiber washer (around the nylon shoulder washer)
c.
Large steel washer
d.
Small steel washer
e.
Torque nut
Be sure to leave at least 5 threads of the threaded rod exposed inside the
frame.
5.
Finger tighten the nut above the raised floor before finger tightening the nuts
below the raised floor.
6.
Finger tighten the nut below the raised floor.
7.
Securely tighten all the nuts above the raised floor with a socket wrench.
910-2969-001 Revision H, February 2007
Preliminary
Frame
side
Finger tighten nuts above
raised floor before tightening
nuts below raised floor
Lock washer
Flat washers
and nut
Tighten nut on
Small washer
Large washer
(4 PLACES)
Nut
Small washer
Large washer
Isolator pad
Raised floor
Concrete floor
04_raised_floor_channel-support
4-15