NOTE: Tighten only until the washer and nuts are flush with the bottom
of the floor tile. DO NOT over tighten.
8.
Replace tiles if necessary.
9.
This procedure is complete.
Next, go to Procedure 4-8 on page 4-19.
How to Anchor on Raised Floor Using Support Channel with Spring Nut
Use the following procedure to anchor the HD frame to the raised floor tiles using
the a support channel with spring nut.
Procedure 4-7.
1.
Ensure that Procedure 4-3, "Create Cable and Anchor Holes for Raised
Floors," on page 4-5 has already been performed.
2.
Insert threaded rods through the frame and the raised floor and into the
spring nut in the support channel as shown in see Figure 4-8.
4-16
Preliminary
Anchor Frame with Support Channel/Spring Nut
How to Install a T1100 AS Frame
910-2969-001 Revision H, February 2007