Loading The Configured Data Into The Drive - Siemens sinamics G120 Operating Instructions Manual

Low voltage inverters chassis devices with cu250s-2 control units and encoder evaluation
Hide thumbs Also See for sinamics G120:
Table of Contents

Advertisement

5.3.5

Loading the configured data into the drive

Loading the configured data into the drive
Procedure with STARTER
Proceed as follows to load the configured data into the drive:
1. Select your drive.
2. Go online:
STARTER compares your configuration with the real inverter. STARTER signals any
differences in the "Online/offline comparison".
Acknowledge the message by pressing the "Load HW configuration to PG" button.
3. Open "Drive Navigator".
4. Select the "Commissioning" button.
5. Click on "Load data to the drive".
6. ☑ In the following screen form, select "After loading copy RAM to ROM".
7. Load your configuration into the inverter.
8. Wait until loading has been completed.
9. Close the "Commissioning" screen form.
You have loaded your configuration into the drive and therefore commissioned the system.
Procedure with Startdrive
Proceed as follows to load the configured data into the drive:
1. Select your drive.
2. Press the "Load to device" button.
3. ☑ In the following screen form, select "Back up parameter assignment in the EEPROM".
4. Load your configuration into the inverter.
5. Wait until loading has been completed.
You have loaded your configuration into the drive and therefore commissioned the system.
Converter with CU250S-2 Control Unit
Operating Instructions, 01/2016, FW V4.7 SP6, A5E31759476B AE
.
5.3 Quick commissioning with a PC.
.
Commissioning
135