Advanced commissioning
6.3 Setpoints
Setting the probe
Parameter
p0490
p0580
p0581
p0582
p0583
p0585
r0586
214
Description
Invert probe
(factory setting 0000bin)
1)
Using the 3rd bit of the parameter value, invert the input signals of digital input 3 for
the probe.
Probe
input terminal (factory setting 0)
1)
Interconnect the probe input with a digital input.
Probe
edge(factory setting 0)
1)
Edge to evaluate the probe signal for the actual measuring speed value
0: 0/1 edge
1: 1/0 edge
Probe
Pulses per revolution (factory setting 1)
1)
Number of pulses per revolution.
Probe
Maximum measurement time (factory setting 10 s)
1)
Maximum measurement time for the probe. If there is no new pulse before the max-
imum measuring time elapses, the inverter sets the actual speed value in r0586 to
zero.
The time is restarted with the next pulse.
Probe
Gear ratio (factory setting 1)
1)
The inverter multiplies the measured speed by the gear ratio before displaying it in
r0586.
Probe
Actual speed value
1)
Result of the speed calculation.
Operating Instructions, 01/2016, FW V4.7 SP6, A5E31759476B AE