Commissioning

5.2 Preparing for commissioning

5.2
Preparing for commissioning
5.2.1

Collecting motor data

Before starting commissioning, you must know the following data:
● Which motor is connected to the inverter?
Note down the Article No. of the motor and the motor's nameplate data.
If available, note down the motor code on the motor's nameplate.
● In which region of the world is the motor to be used?
- Europe IEC: 50 Hz [kW]
- North America NEMA: 60 Hz [hp] or 60 Hz [kW]
● How is the motor connected?
Pay attention to the connection of the motor (star connection [Y] or delta connection [Δ]).
Note the appropriate motor data for connecting.
116
Operating Instructions, 01/2016, FW V4.7 SP6, A5E31759476B AE
Converter with CU250S-2 Control Unit