Replacing A Pad; Replacing A Cabinet Electronic Lock - Huawei FusionModule2000-S User Manual

Smart modular data center
Hide thumbs Also See for FusionModule2000-S:
Table of Contents

Advertisement

FusionModule2000-S Smart Modular Data Center
User Manual
Procedure
Step 1 Label each cable based on the corresponding ports on the smart ETH gateway.
Step 2 Disconnect cables from the smart ETH gateway.
Step 3 Remove the faulty smart ETH gateway from the guide rails.
Step 4 Install the spare smart ETH gateway in the original position and reconnect the
cables.
Step 5 On the ECC800-Pro WebUI, choose Monitoring > System > ECC800 > Controls >
Delete device with communication failure, and click Submit.
Step 6 Log in to the ECC800-Pro WebUI, and edit the plan view by adding new devices.
Step 7 Check the parameters and communication status of the smart ETH gateway to
ensure normal communication.
----End

6.3.11 Replacing a Pad

Impact on the System
The pad cannot be used.
Preparations
Procedure
Step 1 Install the app on the reserved pad (see the commissioning guide) and connect
the pad to the network over the WiFi hotspot of the data center.
Step 2 Specify the user name and password for the app on the reserved pad and log in to
check that the app works properly.
Step 3 Remove the charging cable from the failed pad.
Step 4 Remove the failed pad from the support and install the reserved pad on the
support.
Step 5 Connect the charging cable to the reserved pad.
----End

6.3.12 Replacing a Cabinet Electronic Lock

Prerequisites
Material: electronic lock
Issue 03 (2021-07-15)
Tools: ESD wrist strap, ESD gloves, labels, and marker
Material: pad