Step 5 Check that the installation position meets the requirements.
Step 6 Use a marker to mark hole positions.
Figure 3-10 Positioning
Step 7 Move away the base, use a hammer drill with a φ16 drill bit to drill holes to a
depth of 52–60 mm at the installation position, and install expansion sleeves.
Step 8 Move the base back, install expansion bolts, and partially tighten them.
Step 9 Measure the levelness of the base using a level, as shown by (1) in below figure.
If a base is not level, put washers under it, as shown by (2) in below figure
Figure 3-11 Leveling a base
Step 10 Tighten expansion bolts, as shown by (3) in above figure.
Issue 03 (2021-07-15)
NO TE
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation
32

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c10

Table of Contents