Figure 3-52 Securing general input unit 2
(1) End plug
Properly store the removed end plug and install it on the end busbar trunking
unit.
Step 5 If an MCCB auxiliary lever is delivered, place the MCCB auxiliary lever in the side
fastener of the general input unit for switching on the circuit breaker when
maintaining the general input unit.
Step 6 Install the busbar trunking unit.
Figure 3-53 Securing the busbar trunking units
Step 7 Level the supports and secure them.
1.
2.
Issue 03 (2021-07-15)
NO TICE
Adjust the screw on the top of the support clockwise to raise the support, and
adjust the screw counterclockwise to lower the support.
Use a level to check that the supports are on the same horizontal line.