Step 4 Loosen the screws on both sides of the ECC800-Pro main control module and pull
the handles on both sides of the ECC800-Pro main control module to remove the
main control module.
Figure 6-6 Removing an ECC800-Pro main control module
Step 5 (Optional) Remove the MicroSD card and SIM card from the corresponding slots
of the ECC800-Pro main control module.
Step 6 (Optional) Install the removed MicroSD card and SIM card in the corresponding
slots of the new ECC800-Pro main control module.
Figure 6-7 Installing the MicroSD card and SIM card
Step 7 Install the spare ECC800-Pro main control module in the ECC800-Pro subrack and
tighten the screws on both sides of the ECC800-Pro main control module.
Step 8 Connect the communications cables and antennas to the ECC800-Pro main control
module.
Step 9 Choose Maintenance > Configuration File and import the backup configuration
file, or set parameters for the devices that connect to the ECC800-Pro to ensure
normal communication.
----End

6.3.2.2 Replacing an ECC800-Pro PSU

Prerequisites
Do not touch the terminals in the rear of a removed power supply unit (PSU) to
avoid electric shocks.
Issue 03 (2021-07-15)
D ANGER
Copyright © Huawei Technologies Co., Ltd.
6 Operation and Maintenance
245

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c10

Table of Contents