Download Print this page
Hide thumbs Also See for FusionPower6000:

Advertisement

Quick Links

Hardware Installation
1
Reference Documentation
Item
Reference
UPS
UPS5000-H-(1200 kVA–1600 kVA) User Manual (100 kVA Power Module)
ECC800
ECC800 Data Center Controller User Manual (SmartDC V100R021C10)
Before installation, read the user manual carefully to get familiar with product information and
safety precautions, A 2.4 MW PowerPOD is used as an example to describe the cable connection
in the prefabrication scenario. A 1.6 MW PowerPOD is used as an example to describe the cable
connection in the non-prefabrication scenario.
2.4 MW indoor PowerPOD
(1)
Transformer
(2)
Input and bus tie
cabinet
(4)
Maintenance bypass
(5)
UPS input and bypass
cabinet
cabinets
(7)
Output cabinet
(8)
PAD
(10)
Platform base
1.6 MW indoor PowerPOD
(1)
Transformer
(2)
Input and bus tie
cabinet
(4)
UPS input and bypass
(5)
UPS5000-H-1600 kVA
cabinet
(7)
PAD
(8)
Feeder cabinets
FusionPower6000 V100R021C10 Quick Guide
2
Installing a PowerPOD (Prefabrication Scenario)
Installation Preparations
2.1
1. Remove the fasteners that secure the base to the transportation vehicle based on the site
requirements.
2. Determine the position for installing the PowerPOD on the floor based on the mounting holes
on the platform base. Drill holes and install expansion sleeves.
2.4 MW PowerPOD base dimensions
Hoisting on the First Floor
2.2
(3)
Reactive power
compensation cabinet (SVG)
1. Adjust the PowerPOD in the
(6)
UPS5000-H-1200kVA
installation direction, connect
the steel hoisting ropes, and
(9)
Feeder cabinets
hoist the PowerPOD at the
entrance of the unloading area.
2. When unloading the PowerPOD, use a crane to hoist
one end of the PowerPOD into the room to place it
on the moving dolly at the entrance of the
unloading area, and place the other end on the
wood sleeper. Use a crane to lift the PowerPOD end
placed on the wood sleeper, and use an electric
winch to slowly push the PowerPOD into the room.
3. After the winch pulls the PowerPOD into the room,
place the moving dolly at the rear of the PowerPOD.
(3)
Reactive power
4. After moving to the installation position, place the
compensation cabinet (SVG)
jacks at the I-shaped steel positions on the base of
(6)
UPS output and
the PowerPOD. Lift up the PowerPOD and remove
maintenance bypass
the tank wheel, and then put down the jacks.
cabinet
(9)
Platform base
2.3
Hoisting on a Higher Floor
1. Place the PowerPOD on the hoisting platform and bind it.
2. Adjust the prefabricated PowerPOD in
the installation direction, connect the
steel hoisting ropes, and hoist the
PowerPOD at the entrance of the
unloading area.
3. Connect the steel hoisting ropes to the
Installation dimensions (unit: mm)
rectangular hoisting tool.
4.
Conduct trail hosting. Lift the hook by about 200 mm under the command of the crane
operator and keep it for 5 minutes. Check the status of the crane, legs, and steel ropes.
If any exception is found, put down the PowerPOD immediately and rectify the fault
until the potential risk is eliminated.
5.
Lift the PowerPOD to the hoisting hatch, place the front part of the hoisting platform
indoors, and secure the hoisting platform using two manual hoists.
6. Untie the steel ropes, use
jacks to support the
PowerPOD, and place
eight moving dollies
underneath.
7. Use a pallet truck to pull
the PowerPOD out of the
hoisting platform and
move the PowerPOD to
the installation position.
Winch Pulling
Moving
Wood
rope
dolly
sleeper
03
Binding strap
Hoisting
platform
Steel rope
Rectangular
hoisting tool
Steel rope
PowerPOD
Hoisting platform
PowerPOD
Manual hoist
Pallet truck
Moving dolly
Copyright © Huawei Technologies Co., Ltd. 2022. All rights reserved
.

Advertisement

loading

Summary of Contents for Huawei FusionPower6000

  • Page 1 Feeder cabinets Platform base Winch Pulling Moving Wood Pallet truck Moving dolly rope dolly sleeper Copyright © Huawei Technologies Co., Ltd. 2022. All rights reserved...
  • Page 2 Installing Devices Inside a PowerPOD 1. Move power modules to the reserved positions in the UPS. Rotate the ready switches to the locked state. Secure the power modules. Adjusting screws Copyright © Huawei Technologies Co., Ltd. 2022. All rights reserved...
  • Page 3 Each time you install a phase copper bar, tighten the screws on the copper bar and use a torque d) Install the upper part of the bus clip. wrench to check and mark it based on the standard torque. Then install the other row of copper bars. Copyright © Huawei Technologies Co., Ltd. 2022. All rights reserved...
  • Page 4 BBB box to the battery PE of the UPS or the e) Install the upper part of the bus clip. ground bar in the equipment room based on the site survey. Copyright © Huawei Technologies Co., Ltd. 2022. All rights reserved...
  • Page 5: Power-On Commissioning

    Preparations and App Login 1. Download and install the FusionModule app from Huawei AppGallery. • Huawei AppGallery installed on the PAD: Log in to the Huawei AppGallery client, search for FusionModule, and tap Install. • Huawei AppGallery not installed on the PAD: Verifying the Installation Method 1: Log in to Huawei AppGallery (https://appgallery.huawei.com/), search for...
  • Page 6 Device Name. Click Exit Edit Mode to create a PowerPOD 7. Connecting to the Network. plan view. For details, see the FusionPower6000 V100R021C10 User Manual Copyright © Huawei Technologies Co., Ltd. 2022. All rights reserved...

This manual is also suitable for:

V100r021c10