Procedure
Step 1 Determine the installation position of the server and check whether floating nuts
are installed. If not, install them first.
Figure 3-91 Installing a floating nut
Step 2 Lift the server. This task requires at least two people.
Step 3 Place the server on the guide rails and push it in to the cabinet.
Step 4 When the two mounting ears on the server contact the mounting bars on the
rack, tighten the captive screws on the mounting ears to secure the server.
Figure 3-92 Installing a TaiShan 200 server
Step 5 Connect the power cable to the TaiShan 200 server.
1.
2.
Issue 03 (2021-07-15)
Wear an ESD wrist strap or ESD gloves.
Connect one end of the power cable to the cable port on the AC power
module of the server.