Procedure
Step 1 Determine the cabinet positions based on the layout diagram.
Step 2 Place all cabinets at the correct installation positions.
Step 3 Level the cabinets using a wrench.
● Before leveling a cabinet, measure and ensure that the vertical distance
● If the cabinet heights are different, they may fail to be combined and the entire
Issue 03 (2021-07-15)
Figure 3-13 Cabinet layout diagram
NO TICE
between the top of the 2000 mm high cabinet and the floor is 2000 mm (±3
mm).
smart module may not be sealed properly.
NO TE
● Anchor bolts cannot be removed.
● Anchor bolt adjustment method: Wrench an anchor bolt clockwise to elevate a cabinet,
or wrench an anchor bolt anticlockwise to lower a cabinet.
● Leveling criteria: Level a cabinet using a level to ensure that the cabinet is not tilted.
● A smart cooling product is shown in the figure to demonstrate how to level a cabinet.