Tool: Phillips screwdriver
Materials: 2288X V5 server, guide rail, rubber plug, screw
Procedure
Step 1 Install guide rails.
Figure 3-95 Installing a guide rail
1.
2.
3.
Step 2 Place the server on the guide rails and slide it along the guide rails into the
cabinet.
Step 3 Align the two mounting ears of the server with the mounting bars of the cabinet
and tighten the screws on the mounting ears.
Issue 03 (2021-07-15)
Place a guide rail horizontally at the installation position in the cabinet.
Fix the guide rail using rubber plugs.
a.
In front of the guide rails: If a server is installed using the upper
mounting holes, insert rubber plugs tightly into the holes at the middle. If
a server is installed using mounting holes at the middle, insert rubber
plugs tightly into the upper holes.
b.
Behind the guide rails: Insert rubber plugs tightly into the upper
mounting holes.
(Optional) To enhance the rigidness and seismic-proof performance of a
server, you can install bolts at the rear of flexible guide rails.