8.3.3 (Optional) Installing a Pad

Prerequisites
The pad to be installed has been obtained.
Context
Tool: Phillips screwdriver
Materials: pad and pad charging cable
Skill requirement: common technician
Procedure
Step 1 Adjust the feet at the bottom of the pad mounting support until they are in the same width as
the pad. Route the pad power cable through the cable hole in the pad mounting support and
then connect the cable to the pad.
Step 2 Adjust the feet in the upper part of the pad mounting support and clip the pad into the
mounting support.
Figure 8-16 Installing a pad
----End