Installing the Fabric Interconnect F1-15 in a 4-Post Rack
Unpacking Shipping Containers and Examining Contents
FIGURE 4
Note -
box.
3.
Unpack the Fabric Interconnect chassis and place it on a flat, stable surface
capable of supporting up to 55 pounds (25 kilograms).
Installing the Fabric Interconnect F1-15 in a 4-Post Rack
This section documents how to install the Fabric Interconnect F1-15 in a 4-post equipment rack.
The procedure in this section documents installing a Fabric Interconnect F1-15 by using the
standard rail kit that comes with the Fabric Interconnect. The rail kit is useful as a "rack helper"
to temporarily hold the chassis in place in the rack while attaching rack-mount hardware,
20
Oracle Fabric Interconnect Hardware User's Guide • July 2016
Although not pictured, a cable management assembly (CMA) is included in a separate