The Fabric Board will boot, and when the board completes is bootup and passes to runtime, the
Power LED will glow. The Power LED does not glow until the Fabric Board is in runtime.
Start a management session on the Fabric Interconnect, and log in.
15.
Verify that the Fabric Interconnect recognizes the QDR Fabric Board, by issuing
16.
show hardware then scrolling to the Fabric Board Status section:
The Model column should show the string VP-FRU-FB-QDR
The State column should show UP
The Speed column should show QDR
If these values are not displayed, the Fabric Interconnect does not recognize the QDR Fabric
Board.
17.
Reconnect your servers to the Fabric Interconnect by using QDR cables.
If your DDR Fabric Board had all 24 ports connected, and you will be reconnecting ports 21
through 24 on the QDR Fabric board, you will need to connect an IB expansion switch to a port
on the QDR Fabric Board. The reason for connecting the IB expansion switch is to allow the
servers that were on ports 21 through 24 to be connected to the QDR Fabric Board, which has
only 20 ports.
18.
If your data center is being managed by an SNMP management tool, through the
SNMP Manager, rediscover the devices on the new QDR fabric.
After rediscovering the devices, the procedure is complete. If you encounter problems with this
procedure, you can contact Oracle Technical Support for assistance.
You do not need to return the old Fabric Board. You can keep it as a spare part. But if you
choose to return the old Fabric Board, Oracle can dispose of it. If you choose to return the old
Fabric Board, you can use the shipping container for the QDR Fabric Board to return the DDR
Fabric Board.

Removing and Installing I/O Modules

This section documents how to remove and install an I/O Module. See the appropriate section:
"Remove Fabric Interconnect F1-15 I/O Modules" on page 140
"Remove Fabric Interconnect F1-4 I/O Modules" on page 144
Removing and Installing I/O Modules
Performing Service Tasks
139

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fabric interconnect f1-15Fabric interconnect f1-4

Table of Contents