Prepare for the Procedure

Prepare for the Procedure
1.
Read important information before beginning this procedure. See
Considerations" on page
A fully loaded chassis can be heavy. Always follow safety and safe-handling procedures when
lifting and handling the equipment.
2.
Gather the necessary tools and prepare a grounded work surface for the Fabric
Interconnect chassis.
Properly affix an ESD wriststrap.
3.
Find a second person to assist with removing the chassis from the rack and
4.
installing it when the new FP2 is installed.
Remove the Oracle Fabric Interconnect from a Four-Post
Equipment Rack
You will completely remove the chassis from the rack to get access to the mounting brackets.
Also, you will find it helpful to have a cart or sturdy table nearby on which you can place the
Oracle Fabric Interconnect when it is remove from the equipment rack. Always follow safety
and safe-handling considerations and prerequisites for the procedure.
Remove the screws that secure the chassis to the rack.
1.
2.
Carefully remove the chassis from the rack and set it on an ESD-safe surface.
3.
Continue by removing the old mounting brackets.
"Remove the Old Front Panel" on page
Remove the Oracle Fabric Interconnect from a 27-Inch Sun/
Oracle Equipment Rack
This topic is applicable to Oracle Fabric Interconnects installed in a Sun/Oracle 27-inch
equipment rack.
158
Oracle Fabric Interconnect Hardware User's Guide • July 2016
156.
160.
"Installation

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fabric interconnect f1-15Fabric interconnect f1-4

Table of Contents