13.
Install pressure gauges ranges 0 - 600 bar (0 - 9000
psi) to the hydrostatic pump test ports M1 (1) and
m2 (2).
14.
Remove fuse F01 (1) from the fuse panel.
15.
Turn the key to the start position, to crank the
engine 15 seconds or until 2 - 7 bar (30 - 100 psi)
is seen on the gauge. If pressure does not reach
these levels, check and fill the PTO oil level.
IMPORTANT: Only crank the engine for a maximum
of 30 seconds at a time. Wait at least 1 minute before
recranking to avoid damaging the starter motor.
16.
Shift the transmission in neutral and crank the
engine with the starter motor until a pressure gauge
reading of 2.0 bar (29 psi) is obtained.
17.
Fill the PTO gearbox to maximum level.
18.
Install fuse F01 (1) into the fuse panel.
CAUTION
M583 - Make sure everyone is clear of the machine
before starting the engine.
CAUTION
M142A - Never operate the engine in a closed building.
Proper ventilation is required under all circumstances.
POWER TRAIN - TRANSMISSION Hydrostatic
9681 1 27/05/2004
C.20.F / 16
9
10033621A5
10
50020070A5
11
50020070A5