4.
On the Left Hand Side, use an adjustable jack stand
(3) to help share the load of the gearbox. The stand
should have at least a 907 kg (2000 lb) capacity.
Install rubber O-ring on shaft (2) so collar (1) does
not slide off the shaft during rotation.
NOTE: The Gearbox is heavy. Use extreme caution
when working around. Be sure to use adequate lifting
equipment and hardware.
5.
Torque all plated M16 bolts to 230 Nm (170 lb ft)
and all un-plated bolts to 176 Nm (130 lb ft).
POWER TRAIN - POWER COUPLING Fixed coupling
9679 1 27/05/2004