Initial Functional Tests - Ametek Elgar ReFlex Power Operation Manual

Table of Contents

Advertisement

ReFlex Power™
I
5.5.5
NITIAL
P
-O
OWER
N
1. Ensure that the AC/DC input service is disconnected.
2. Install the interface cable between the host controller and the ReFlex
3. Connect an appropriate output load to one or more of the FPDC power
4. Configure the host controller for communications with the ReFlex
5. Turn on the AC/DC input service.
6. The modules will first execute a power-on self-test. Also the internal fans
7. Verify communications with the ReFlex Power™ Controller module by
8. The ReFlex Power™ Controller module should respond with its
9. Verify communications with the ReFlex Power™ FPDC power supply
10. The FPDC power supply module should respond with its identification
S
TANDALONE
1. Connect the output for standalone operation per the section, Standalone
2. Connect appropriate instrumentation for measuring the output voltage and
3. Perform the power-on verification test per the preceding section, Power-On
4. Turn on the isolation and remote sense relays
5. Turn on the outputs
6. Measure the output voltage and current with the external instruments.
7. Turn off the output with the following command:
M380056-01 Rev L
F
T
UNCTIONAL
ESTS
C
HECK
Power™ Controller module.
supply module outputs.
Power™ Controller module.
are run at maximum speed for several seconds, and then back to slow
speed.
issuing an SCPI *IDN?,
identification string.
module by issuing an SCPI *IDN[n]?, where "n" is a channel number
that corresponds to the slot of the ReFlex Power™ Mainframe where the
module is located, counting left to right, 1 through 12.
string. The default settings of the module will not be affected.
C
O
ONFIGURATION
Configuration.
current, as well as a load.
Check.
*RST[n]
C
PERATION
HECK
Fixed Power DC Power Supply
5-27