Commissioning

5.3 Preparing for commissioning

5.3
Preparing for commissioning
Data for a standard induction motor
Before starting commissioning, you must know the following data:
• Which motor is connected to the converter?
Note down the Article No. of the motor and the motor's nameplate data.
If available, note down the motor code on the motor's nameplate.
Figure 5-2
• In which region of the world is the motor to be used?
- Europe IEC: 50 Hz [kW]
- North America NEMA: 60 Hz [hp] or 60 Hz [kW]
• How is the motor connected?
Pay attention to the connection of the motor (star connection [Y] or delta connection [Δ]).
Note the appropriate motor data for connecting.
5.3.1

Converter factory setting

Motor
With its factory settings, the converter is set up for an induction motor suitable for the power
rating of the Power Module.
Converter interfaces
The inputs and outputs and the fieldbus interface of the converter have specific functions when
set to the factory settings.
78
Example of the rating plate for a standard induction motor
Factory settings of the inputs and outputs (Page 57)
Converter with the control units CU240D-2