Avaya g700 Installation And Upgrades page 91

Media gateway and media server
Hide thumbs Also See for g700:
Table of Contents

Advertisement

The G700 is shipped with 3 sets of four mounting screws. Choose the set of screws that
match the screw holes in the rack being used.
The G700 weighs 22.5 pounds (10 kg) empty and between 27 and 34 pounds (between 12
and 16 kg) when equipped with media modules. Two people may be needed to mount the
G700 Media Gateway in the rack.
Figure 7: Rack Mounting
To mount the G700 media gateway in the rack
1. Position the G700 in the rack.
Assure that there is adequate ventilation.
2. Verify that the screw holes are aligned with the rack hole positions.
3. Insert the mounting screws.
Use two screws on each side.
4. Tighten the mounting screws.
Avoid overtightening.
5. Verify that ventilation vents are not obstructed.
6. Repeat to add other G700 media gateways to the rack, as described in the planning
documents.
About installation and cabling
Issue 8.1 June 2005
91