(3) MELSECNET/H connection (PLC to PLC network) and MELSECNET/10 connction (PLC to PLC
network)
(a) For coaxial cable
• Strip the outer insulation layer at both ends of the cable by the length shown below to expose
the outer braided shield for grounding. (For grounding with cable clamps (refer to Section
5.4.3.))
• Attach ferrite cores to the cable in the positions as illustrated below.
GOT side
130 or
less
(5.12)
230 or less
(b) For optical fiber cable
• Processing of the cable is not required.
(4) CC-Link connection (Intelligent device station)
Strip the outer insulation layer at both ends of the cable by the length shown below to expose the
braided shield for grounding. (For grounding with cable clamps (refer to Section 4.4.3.))
• Attach ferrite cores to the cable in the positions as illustrated below.
• CC-Link dedicated cable for connecting the GOT and PLC.
GOT side
130
(5.12)
230 or less
• CC-Link dedicated cable for connecting the GOT and GOT
GOT side
130
(5.12)
230 or less
5
5.4 Precautions for Wiring/Connecting the EMC Directive-Compliant Product
- 20
5.4.2 Processing connection cables
(ZCAT3035-1330)
40
(9.06)
(1.57)
Ferrite Core
(ZCAT3035-1330)
40
(9.06)
(1.57)
Ferrite Core
(ZCAT3035-1330)
40
(9.06)
(1.57)
Ferrite Core
40
(1.57)
40
(1.57)
40
(1.57)
PLC side
130 or
less
(5.12)
400 or less
(15.75)
Unit : mm (inch)
PLC side
130
(5.12)
400 or less
(15.75)
Unit : mm (inch)
GOT side
130
(5.12)
230 or less
(9.06)
Unit : mm (inch)