MMB Web-UI (Web User Interface) Operations
1.7 [System] Menu for PRIMEQUEST 2800B2/2800B

1.7.8 [Schedule] Menu

The [Schedule] menu has the [Schedule Control] and [Schedule List] windows. This section describes the
windows and the operation.
Note
As mentioned below, there may be a delay in the time recorded in SEL compared to the time reserved for
scheduled operations.
After checking the configuration and after performing the start up preparation process, it takes some
time until the power is ON. In this case, the SEL display is delayed about from six seconds up to 8
seconds than the time reserved for the scheduled operations.
The shutdown instructions from MMB to OPERATING SYSTEM take certain time from the set time.
However, the following interval times may be changed under the various conditions like setting and the
configuration.
Interval time until shutdown instructions reaches OS from MMB.
Interval time until MMB notifies SEL begin shutdown after OS begins shutdown.
Even if the [Power on Delay] is 0 seconds, it takes about 30 seconds ~ 70 seconds from starting the
power on up to the reset.

1.7.8.1 [Schedule Control] window

In the [Schedule Control] window, the setting related to the schedule can be set for system.

FIGURE 1.126 [Schedule Control] Window

303