Installation base

1) Prepare a sufficiently rigid and stable installation base, taking account of
the robot weight including the end effector (gripper), workpiece and reac-
tion force while the robot is operating. The maximum reaction force (see
Fig. 3-1) applied to the X-axis and Z-axis of each robot during operation is
shown in the table below. These values are an instantaneous force applied
to the robot during operation and do not indicate the maximum load capa-
city.
2) The parallelism of the installation base surface must be machined within
a precision of ±0.05mm/500mm. The robot base mount must be installed
facing down and in a level position (except ceiling-mount models which
should be installed with the base mount facing up).
3) Tap holes into the surface of the installation base. For machining dimen-
sions and positions, refer to the dimensional outlines listed in our robot
catalog.
The maximum reaction force
F
max
X
N
Robot Model
R6YXCH250
305
R6YXCH350
330
391
R6YXCH400
708
R6YXC500
R6YXC600
735
R6YXC700
1653
1707
R6YXC800
1618
R6YXC1000
Fxmax
Fzmax
Load
Fig. 3.1 Maximum reaction force applied during operation
3-3
M
max
X
kgf
Nm
kgfm
31
56
6
34
56
6
40
56
6
72
137
14
75
137
14
169
304
31
174
304
31
165
333
34
Mxmax
CHAPTER 3 Installation
F
max
Z
N
kgf
40
4
40
4
40
4
89
9
89
9
159
16
159
16
127
13