Trial Operation

After making installations, adjustments, inspections, maintenance or repairs to
the robot, make a trial run using the following procedures.
(1) If a safeguard enclosure has not yet been provided right after installation of
the robot, rope off or chain off around the movement area of the manipula-
tor in place of the safeguard enclosure, and observe the following points.
1. Use sturdy, stable posts which will not fall over easily.
2. The rope or chain should be easily visible by everyone around the robot.
3. Place a sign to keep the operator or other personnel from entering the
(2) Check the following points before turning on the controller.
1. Is the robot securely and correctly installed?
2. Are the electrical connections to the robot correct?
3. Are items such as air pressure correctly supplied?
4. Is the robot correctly connected to peripheral equipment?
5. Have safety measures (safeguard enclosure, etc.) been taken?
6. Does the installation environment meet the specified standards?
(3) After the controller is turned on, check the following points from outside
the safeguard enclosure.
1. Does the robot start and stop as intended? Can the operation mode be
2. Does each axis move as intended within the soft limits?
3. Does the end effector move as intended?
4. Are the signal transmissions to the end effector and peripheral equip-
5. Does emergency stop work?
6. Are the teaching and playback functions normal?
7. Are the safeguard enclosure and interlock working as intended?
8. Does the robot move correctly during automatic operation?
movement range of the manipulator.
selected correctly?
ment correct?
CHAPTER 1 Using the Robot Safely
1-11