Performing Insulation And Dielectric Strength Tests - Huawei FusionPower6000 3.0 User Manual

Table of Contents

Advertisement

FusionPower6000 3.0
User Manual (Not Against a Wall)
Figure 5-1 Commissioning process

5.2 Performing Insulation and Dielectric Strength Tests

There are two test coverages:
● When removing cables and components or performing insulation and dielectric
● After the insulation and dielectric strength tests are complete, powering on the
Issue 03 (2023-02-08)
Test not involving loads: During the test preparation, turn off the switches of
all MCCB output modules in the maintenance bypass cabinet and feeder
cabinet.
Test involving loads: During the test preparation, turn on the switches of all
MCCB output modules in the maintenance bypass cabinet and feeder cabinet.
NO TICE
strength tests, failure to comply with the procedures may damage the
equipment, and the losses caused are not covered under warranty.
equipment without restoring the cables and components based on the
electrical diagrams and records may damage the equipment, and the losses
caused are not covered under warranty.