Cabinet
Feeder cabinet
Step 8 Route the UPS parallel cable and communications network cable through the
cable hole in the enclosure frame.
Step 9 Install screws on the copper bars of the positive and negative battery terminals in
the UPS cabinet.
Figure 4-19 Installing screws on the copper bars of the positive and negative
battery terminals in the UPS cabinet
Step 10 Combine adjacent enclosure frames.
Figure 4-20 Combining frames
----End
Issue 03 (2023-02-08)
Screw
M6X16
M8X25
M6X16
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation and Cable Connection
Torque
2 N·m
13 N·m
2 N·m
Quantity
6 PCS for a
cabinet with a
width of 800 mm
or less
4 PCS
4 PCS
4 PCS