Step 4 Set the maintenance bypass switch on the maintenance bypass cabinet to the
TEST position and perform switch-on and switch-off impact tests.
Step 5 Set the maintenance bypass switch on the maintenance bypass cabinet to the
CONNECT position and perform switch-on and switch-off impact tests.
Step 6 Turn on the maintenance bypass switch. The PDC Maint. breaker closed and
Bypass mode alarms are displayed on the UPS LCD, and the UPS does not allow
the inverters to start.
Step 7 Turn off the maintenance bypass switch. The PDC Maint. breaker closed alarm
disappears on the UPS LCD. Check that the UPS is working in bypass mode by
viewing the system running status diagram.
Step 8 Press and hold the Push OFF button on the maintenance bypass switch, rotate the
mechanical lock key counterclockwise to the vertical direction, remove the key,
and store it properly.
Step 9 Start all UPS inverters. On the UPS LCD, choose Common Functions > Inv. ON or
Common Functions > Parallel Inv. ON. The UPS transfers to inverter mode.
----End
5.8 Commissioning Feeder Switches
If the centralized monitoring board is powered by the PSU or cascaded 48 V power
supply and the WAN1/WAN2 port is connected to the PoE port, the power switch
status on the UI of the smart ETH gateway will switch between power-on and
power-off. This is a normal phenomenon and does not affect system services or
functions.
Step 1 Check that the switches on the load side are turned off.
Step 2 Turn on the feeder switches one by one and ensure that the input voltage of the
load switches meets the requirements.
----End
5.9 Networking Commissioning
5.9.1 Preparations and WebUI Login
Prerequisites
●
●
●
Issue 03 (2023-02-08)
CA UTION
Supported operating system: Windows 7 and later versions
It is recommended that the screen resolution be 1366 x 768 or higher.
Browser: Chrome, Firefox 32, Internet Explorer 11 or later