Huawei FusionModule1000A20 Installation Manual
Huawei FusionModule1000A20 Installation Manual

Huawei FusionModule1000A20 Installation Manual

It solution
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

Quick Links

FusionModule1000A20 IT Solution
V200R002C10
Installation Guide (2016.05, AI
Version)
Issue
02
Date
2017-01-10
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei FusionModule1000A20

  • Page 1 FusionModule1000A20 IT Solution V200R002C10 Installation Guide (2016.05, AI Version) Issue Date 2017-01-10 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a potentially hazardous situation which, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. NOTICE is used to address practices not related to personal injury. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 4 Issue 02 (2017-01-10)  Adjusted the architecture of the manual.  Optimized the content of the manual. Issue 01 (2016-08-30) This issue is the first official release. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    7 Installing External Cooling Devices ..................30 7.1 Process for Installing External Cooling Devices ......................30 7.2 (Optional) Installing Auxiliary Water Refill Devices ....................30 7.2.1 Installing a Water Tank ............................30 Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 6 10.6.1 DPJ End Connector Cable Inlet ..........................74 10.6.2 Waterproof Metal Connector Cable Inlet ....................... 77 10.7 Attaching Cable Labels ............................. 80 10.8 Verifying the Installation............................81 Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 7 13.2 Removing Transport Protection Materials for Fire Extinguishing Devices .............. 89 14 Installation Verification ......................91 A Paint Repair ..........................93 B Cleaning Containers ........................97 C Acronyms and Abbreviations ....................98 Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 8: Installation Guide Usage

    Precautions provided in this document are only supplementary to the local laws and regulations governing the FusionModule1000.  Unless otherwise specified, dimensions of devices in this document are by default height x width x depth. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 9: Site Requirements

    The concrete platforms must be at least 100 mm higher than the ground, and the levelness deviation must be less than 10 mm. The height depends on the local drainage capability and climate. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 10: External Environment Requirements

     The power input current must be 160 A. Table 2-1 describes the voltage and frequency requirements. Huawei provides products based on the voltage system and frequency required by customers. Table 2-1 Power input voltage and frequency requirements Frequency Input Voltage (V)
  • Page 11: Water Refill And Drainage Requirements

     Dispose of water drained out of containers in accordance with local laws and regulations. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 12: Pipe Anti-Freezing

    The electric trace heater will be closed until the temperature of the pipe surface rises to 5° C or higher. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 13 FusionModule1000A20 IT Solution Installation Guide (2016.05, AI Version) 2 Site Requirements  The electric trace heater is powered by the customer's power supply. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 14: General Installation Process

    FusionModule1000A20 IT Solution Installation Guide (2016.05, AI Version) 3 General Installation Process General Installation Process Figure 3-1 General installation process Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 15: Installation Preparations

    FusionModule1000A Describes how to use and Download this document V200R002C00&C10 maintain outsourced from Outsourced Component components. http://3ms.huawei.com. If Document Package the link is unavailable, contact onsite Huawei Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 16: Obtaining Tools And Materials

    Table 4-2 Tools and materials Categor Tools and Materials Fastenin Phillips screwdriver Flat-head screwdriver Phillips screwdriver M4 g tools (M5, M6, and M8) (2–5 mm) (length < 100 mm) Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 17 Torque wrench Solid wrench Socket wrench Needle-nose pliers Diagonal pliers RJ45 crimping tool Crimping tool Wire stripper Hydraulic pliers Wring tools Wire clippers Pliers Cable reel Heat gun Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 18 Metal cutter Hacksaw Pipe connecti Pipe wrench Hot melt device on tools Utility knife Claw hammer Rubber mallet Device installati on tools Scissors Ladder Step ladder (2 m) Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 19 Right angle Measuring tape (5 m) Level Measuri ng tools Long leather measuring Straight steel ruler Steel measuring tape tape Cleaning Brush Paint brush Vacuum cleaner tools Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 20  Preventive measures should be applied before installation to avoid water seepage into containers and equipment in the case of a sudden change in the weather. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 21: Checking Personnel Requirements

     Huawei will not be liable for any consequences caused if the installation environment does not meet the requirements.  Mark the security zone: Use red caution belts to delimit a security zone, clean up obstacles in that zone, and place construction signs and warning signs in eye-catching positions.
  • Page 22: Installing A Container

    Before installing the containers, determine the installation position and direction based on actual situations. Obtain the container base layout diagram from quick installation guide for the solution in use, and strictly follow the diagram when installing the bases. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 23 Step 4 Referring to the container layout diagram, draw the longitudinal and latitudinal reference lines from the center of bases with a straight steel ruler, right angle, and ink fountain. Step 5 Place bases based on the reference lines. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 24 There are eight mounting holes in a base. Mark all the hole positions. Step 7 Move the container base away, and drill a hole in the specified position using a hammer drill, as shown by (1) in Figure 5-4. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 25 Remount the flat washers, spring washers, and nuts on the expansion bolts and tighten the expansion bolts to a torque of 190 N· m using a torque wrench. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 26 After the installation is complete, check whether the container bases are installed in compliance with the container installation position diagram. If any inconsistency is found, adjust the container bases. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 27: Hoisting And Securing Containers

    Remove the ropes after ensuring that the container is placed evenly on the four bases. Preparations Tools: crane, torque wrench, jack, steel hoisting rope, level Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 28 210 N· m using a torque wrench, as shown in Figure 5-8. Before you tighten twistlocks, ensure that the twistlocks lock the container. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 29: Grounding Containers

    5.3 Grounding Containers Prerequisites  Containers have been installed.  The grounding positions have been specified.  The grounding requirements have been specified. Preparations Tool: torque wrench Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 30 5-10. Ground cables should be protected by a plastic-coated metal hose. Figure 5-10 Installing a ground cable ----End Follow-up Procedure Check that the containers are grounded as required by 2.5 Grounding Requirements. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 31: Installing External Accessories

    Skill requirement: common technician For the diagram, see the quick installation guide for the solution in use. Procedure Step 1 Remove the temporary door handle using a hex key. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 32 Step 2 Take out the stainless steel door handle and install it in the required position using a hex key. Figure 6-2 Installing a door handle ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 33: Optional) Installing Step Ladders

    Tools: adjustable wrench, torque wrench, marker, hammer drill, claw hammer, vacuum cleaner Materials: step ladder, expansion bolt Document: step ladder layout diagram Skill requirement: common technician Procedure Step 1 Adjust the step ladder height. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 34 Step 5 Hammer the expansion bolt into the hole vertically until the flat washer is flush with the ground, as shown by (3) in Figure 6-5. Step 6 Remove the nut, spring washer, and flat washer, as shown by (4) in Figure 6-5. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 35 Remount the flat washers, spring washers, and nuts on the expansion bolts and tighten the expansion bolts using a torque wrench. Figure 6-6 Securing a step ladder ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 36: Installing A Fire Hammer

    Step 1 Take out a fire hammer from the fitting bag. Step 2 Install the fire hammer in the specified position. Figure 6-7 Installing a fire hammer ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 37: Installing External Cooling Devices

    The water tank and pipe layout and installation platform has been planned.  A water tank with required capacity and water pipes with a required flow rate have been prepared. Preparations Tools: adjustable wrench, protective gloves Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 38: Installing A Water Pump

    There is no requirement on the sequence for installing the water tank and water pump.  Apply anti-freezing measures in low-temperature areas. For details, see 2.7 Pipe Anti-freezing. ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 39: Connecting Water Refill And Drainage Pipes

    Procedure Step 1 Remove the silver paper from the plug of the container water refill valve. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 40: Installing Drainpipes

    The drainpipe installation plan for the FusionModule1000 meets the drainage requirements and principles. Preparations Tools: protective gloves and hot melt device Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 41 Step 3 Wrap the exposed parts of the pipes with 10 mm thick thermal insulation foam. ----End Follow-up Procedure Verify that the PP-R pipe connector is closely melted with the pipes at both ends. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 42: Optional) Installing External Cable Trays

    Figure 8-1 Process for installing external cable trays 8.2 Installing External Cable Tray Supports Prerequisites  Containers have been installed.  Installation positions for external cable tray supports have been determined. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 43 Exercise caution when placing and handling cable tray supports because they are tall and heavy. Step 4 Mark the hole positions for installing cable tray supports on the concrete platform using a marker. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 44 (3) in Figure 8-3. Step 8 Remove the nut, spring washer, and flat washer, as shown by (4) in Figure 8-3. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 45 Remount the flat washers, spring washers, and nuts on the expansion bolts and tighten the expansion bolts using a torque wrench. Figure 8-4 Securing a cable tray support ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 46: Securing Cable Trays

    When you place a cable tray on supports, ensure that both ends of the cable tray are on the supports. Step 2 Adjust the cable trays, and secure them to the cable tray supports using bolts. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 47 8 (Optional) Installing External Cable Trays Figure 8-5 Securing cable trays Step 3 Adjust the cable trays, and secure two parallel cable trays using M8x80 bolts. Figure 8-6 Installing parallel cable trays Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 48: Installing Ground Lugs For Cable Trays

    Step 2 Install the ground lugs reserved during groundwork construction onto the cable tray supports using a torque wrench. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 49 Verify that cable tray grounding conforms to design requirements, and that cable trays in each row have at least two points securely grounded with a ground resistance within 10 ohms. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 50: Installing Devices Inside Containers

    Figure 9-1 Process for installing internal devices 9.2 Installing Fire Extinguishing Devices 9.2.1 (Optional) Installing Standard Fire Extinguishing Devices 9.2.1.1 (Optional) Installing the Fire Cylinder (Standard) Prerequisites  The container has been installed. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 51 Do not move the fire cylinder over a long distance by hands. Step 2 Remove the hold hoops pre-installed on the fire cylinder. Step 3 Move the fire cylinder to the installation position and secure it. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 52 Figure 9-2 Positions of the threaded adapter and high-pressure hose (1) Threaded adapter (2) High-pressure hose Step 5 Connect the cable to the pressure announciator, as shown in Figure 9-3. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 53 Before connecting the cable, verify that the cable is the electromagnetic valve cable by checking the cable label.  Connect the red wire to the red wire, and connect the black wire to the black wire. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 54: Charging Extinguishant

    Documents: fire extinguishing device installation position diagram (standard) Skill requirement: fire engineer Procedure Step 1 Replace the electromagnetic valve of the fire cylinder with a camshaft device. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 55 Figure 9-7. Then open the fire cylinder valve, and adjust the platform scale to make it balanced. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 56 Record the weight of charged extinguishant on the corresponding position of the fire cylinder label using a marker. Step 10 Reinstall the safety pin and electromagnetic valve. ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 57: Installing Batteries For The Fire Alarm Control Panel (Standard)

    Step 3 Connect the batteries using the reserved power cables. Distinguish the positive and negative battery terminals when connecting battery cables. Figure 9-8 Connecting battery cables Step 4 Tighten the fixing plate using a Phillips screwdriver. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 58: Optional) Installing Fire Extinguishing Devices (Ce)

    Materials: fire cylinder, high-pressure hose, sealing tape, pressure operated switch hose and its accessory, threaded adapter, I-shaped connection pipe Documents: fire extinguishing device installation position diagram (CE) Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 59 Remove the protective cover at the threaded adapter position of the container valve, and connect the threaded adapter to the fire cylinder, as shown by (1) in Figure 9-10. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 60 Verify that the electric control head ejector is reset. If the ejector is not reset, press the ejector. If the ejector is not reset, extinguishant may be released due to misoperations. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 61: Installing Batteries For The Extinguishant Control Panel (Ce)

    For the diagrams, see the quick installation guide for the solution in use. Procedure Step 1 Open the door of the fire control box, and install batteries in the reserved position. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 62 Do not connect the red positive cable until the power-on commissioning.  Ensure that battery cables for the extinguishant control panel are connected to correct polarities. Figure 9-13 Connecting cables to the extinguishant control panel batteries ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 63: Installing Power Distribution Devices

    Step 1 Determine the battery pack installation position based on the power supply and distribution device layout diagram and cabinet configuration table. Step 2 Install the battery pack. Install floating nuts on the cabinet. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 64 Step 4 Connect battery pack power cables based on the battery pack wiring diagram. Before connecting cables, ensure that all UPS-related circuit breakers are OFF. (Optional) Remove the cover from a cable distribution box. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 65: Installing Cooling Devices

    Preparations Tools: Phillips screwdriver, band clamp, ESD floor suction plate Materials: dehumidifier, pipes Documents: cooling device layout diagram, documents delivered with the dehumidifier Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 66 PDC. ----End Follow-up Procedure Verify that the dehumidifier is reliably installed. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 67: Optional) Replacing The Voltage Jumper For A 20 Kw Air Conditioner

    Step 3 Remove the 380 V voltage jumper on the side of the electric control box of the air conditioner, as shown by 1 in Figure 9-18. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 68 Step 4 Connect an appropriate voltage jumper to the voltage jumper port. Figure 9-19 shows a voltage jumper. Figure 9-19 Voltage jumper Step 5 Reinstall the air filter and rear door of the air conditioner. ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 69: Installing Monitoring Devices

    Step 5 Loosen screws on the camera cover using a screwdriver and remove the cover. Step 6 Use a Phillips screwdriver to secure the camera body, as shown by (1) in Figure 9-20. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 70: Installing The Rh2288 Server

    The RH2288 server to be installed has been obtained. Preparations Tool: Phillips screwdriver Materials: RH2288 server Documents: monitoring device installation position diagram, cabinet configuration tables Skill requirement: common technician Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 71 Figure 9-22 Installing the RH2288 server Step 4 Find the pre-installed power cables with correct labels, and connect the cables to the power input ports of the RH2288 server. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 72: Installing A Vcn500

    Step 2 Take a VCN500 out of the fitting bag. Step 3 Place floating nuts into the specified square holes. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 73 Figure 9-25 Placing a VCN500 Step 5 Tighten the captive screws in the ears using a Phillips screwdriver to close the mounting ear buttons. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 74 (1) Ground terminal (2) GE2 port (3) Power input port (4) GE1 port ----End Follow-up Procedure Verify the VCN500 installation and ensure that cables are correctly connected. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 75: Cable Installation Techniques

    FusionModule1000A20 IT Solution Installation Guide (2016.05, AI Version) 10 Cable Installation Techniques Cable Installation Techniques 10.1 Process for Installing External Cables Figure 10-1 Process for installing external cables Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 76: Measuring Cables

    Preparations Tools: protective gloves, marker Material: cable Document: none Skill requirement: common technicians Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 77: Routing Cables Through A Plastic-Coated Metal Hose

    Some external cables for the FusionModule1000 are long and have a large diameter. Assign sufficient people to route cables especially armored cables through a plastic-coated metal cable if no assistant tool is available onsite. Preparations Tools: protective gloves Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 78: Cable Layout

     The selected cables except armored cables have been routed through a pipe. Preparations Tools: step ladder, protective gloves, safety helmet Materials: cable tie and rubber washer Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 79 Step 4 After cables are adjusted, bind the cables with cable ties. Figure 10-2 shows a typical cable layout. Cables must be bound neatly, and cable ties must be secured evenly and properly in the same direction. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 80: Optional) Routing Cables Through A Buried Pipe

    Document: none Skill requirement: skilled technicians Operation Method Route the measured cables through the cable pipe reserved during groundwork, and route the cables through the feeder windows. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 81: Routing Cables Into Feeder Windows

    Cables need to be routed into a feeder window using DPJ end connectors. Context A DPJ end connector consists of a body, ferrule, guarding, and cover lock nut. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 82 Step 2 Remove the cover lock nut, guarding, and ferrule of the DPJ end connector using a wrench, and remove the sealing rubber washer inside the connector. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 83 Step 4 Screw the ferrule into the plastic-coated metal hose. Figure 10-8 Installing DPJ end connectors Step 5 Route the cable into the container through the body of the DPJ end connector. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 84: Waterproof Metal Connector Cable Inlet

    Step 8 Spray water to test the waterproof performance of the DPJ end connector. ----End 10.6.2 Waterproof Metal Connector Cable Inlet Only armored power cables among FusionModule1000 external cables are routed into feeder windows using waterproof metal connectors. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 85 Figure 10-11 Disassembling a waterproof metal connector (1) Plug Step 2 Route a cable into the container through the waterproof metal connector, as shown in Figure 10-12. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 86 Step 3 Wrap four circles of waterproof tape around the joint between the cable and the waterproof metal connector. Figure 10-13 Wrapping sealing tape Step 4 Tighten the waterproof metal connector using a dedicated wrench. Figure 10-14 Securing the waterproof metal connector Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 87: Attaching Cable Labels

    Tool: pen Materials: labels Document: none Skill requirement: common technician Procedure Step 1 Combined with field case preparation or production label based on a random shipping label. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 88: Verifying The Installation

     Cables are neat, pleasing, and not coiled. Extra parts are cut off.  Cable ties do not overlap, and the joints are evenly cut without burrs. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 89 Cable routes are straight and smooth, and do not intersect inside a cabinet. Feeder window Observe External cables are securely installed on installation feeder windows and are tested by spraying water. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 90: Connecting External Cables

    ----End 11.2 (Optional) Installing External Output Power Cables Prerequisites  Containers and external cable trays have been installed.  Power distribution devices have been installed inside containers. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 91: Optional) Installing External Signal Cables

    Step 3 Install the signal cables by following the instructions in 10 Cable Installation Techniques. ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 92: Optional) Installing Peripheral Monitoring Devices For Containers

    For details about ports reserved for peripheral monitoring devices for a container, see the quick installation guide and initial configuration parameter manual for the solution in use. For details about the installation methods, see documents delivered with the devices. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 93: Removing Transport Protection Materials

    To prevent damage to aisle floors in the FusionModule1000, it is recommended that you remove the protective films after the FusionModule1000 is installed. Step 3 Remove the transport fasteners from the air conditioner compressors. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 94 Transport fasteners must be removed from the air conditioner cabinets and compressors; otherwise, the air conditioners may not work properly. Remove transport fasteners from the air conditioner cabinets. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 95 15 N· m using a torque wrench, as shown by in Figure 13-3. Remove the fixing bolts from the compressor mounting ears using a 13# solid wrench and take out the fasteners. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 96: Removing Transport Protection Materials For Fire Extinguishing Devices

    Preparations Tools: step ladder Materials: none Documents: fire extinguishing device layout diagram Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 97 Fire extinguishing system Smoke detector Red cover, securing tape (CE) Heat detector Red cover, securing tape StroBell Securing tape Buzzer Securing tape Emergency light Securing tape ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 98: Installation Verification

     Flat washers and spring washers of all wiring terminals are securely installed.  Cables are routed in the way convenient for future maintenance and expansion. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 99 Installation of The number and position of external Observe. external accessories accessories installed conform to design requirements. Labels Observe. All labels are correct, clear, and complete. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 100: A Paint Repair

    2+Step 3+Step material exposed) brush or spray gun LOGO and pattern If the logo and patterns are damaged, Huawei provides the damage repainting solution, and a local advertisement coating supplier repairs the paint 1. If a dent is less than 100 mm...
  • Page 101 Then wipe off the alcohol with a piece of clean cotton cloth. Figure A-3 Removing smudges Step 3 Paint the first layer of zinc-rich primer on the damaged area using a brush or spray gun. Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 102 Step 4 If a small area is damaged, manually spray paint or brush paint on the area for two times. If a large area is damaged, spray paint using a spray gun on the area for two times. Figure A-5 Manual paint spray Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 103 The color difference δE should not be greater than 3 (use a colorimeter to measure the color difference). Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 104: B Cleaning Containers

    Clear dust, rain marks, or stains on the outer panels of containers using a long-handled soft brush dipped with alkaline or neutral detergent. Wash the container with clean water. It is recommended that you clean the containers once every quarter. ----End Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 105: C Acronyms And Abbreviations

    Acronyms and Abbreviations automatic transfer switch Conformite Europende rack power distribution unit rPDU surge protective device Transmission Control Protocol/Internet Protocol TCP/IP uninterruptible power system video cloud node Issue 02 (2017-01-10) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.

Table of Contents