FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) Issue Date 2020-12-20 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) About This Document About This Document Purpose This document describes the initial configuration parameters of the data center as well as the precautions, processes, parameters, and drawings for installing the data center.
Page 4
FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) About This Document Symbol Description Indicates a potentially hazardous situation which, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. NOTICE is used to address practices not related to personal injury.
This chapter describes the notes for using the quick guide. ● Before the installation, check whether the materials are intact according to the packing list. If there is any problem, contact Huawei technical support. ● This document provides only the initial configuration parameters required for data center commissioning and O&M as well as the drawings and parameters...
Page 7
FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) 1 Quick Guide Usage ● The figures provided in this document illustrate only installation and connection methods. The actual product appearance prevails. ● Unless otherwise specified, the unit for the dimensions in the figures provided in this document is mm by default.
Page 9
Checklist of Devices Installed Onsite Installation Subcategory Item Diagram ID Diagram Name Sequence Installing Pre-fab. Module Bases Installing Pre-fab. Removing the Pre-fab. Module Modules (Base NO.S002 Site Space and Pre-fab. Module Cover Installing Pre- Solution) Installation Position Diagram fab. Modules Hoisting and Securing Pre-fab.
Page 10
Installation Subcategory Item Diagram ID Diagram Name Sequence Installing Power Battery Pack Wiring Diagram Supply and Installing Battery Packs NO.P010 (Without iBAT) Distribution Devices Monitoring Device Installation NO.M004 Position Diagram ECC800 3G/4G Antenna NO.S017 Installation Position Diagram Installing ECC800 Accessories ECC800 3G/4G Antenna Cable NO.S018 Routing Diagram...
Page 11
NO.S002 Site Space and Pre-fab. Module Installation Position Diagram Concrete platform Single-capacity base Concrete platform Ground Concrete platform Concrete platform Note: 1. The concrete platform needs to support a pre-fab. module with the maximum weight of 25,000 kg. The recommended area of a single-capacity base installed on the ground).
Page 12
NO.S003 Pre-fab. Module Grounding Position Diagram...
Page 13
NO.S005 External Cable Tray Installation Position Diagram Single-capacity base Concrete platform Ground...
Page 14
NO.S007 Rain and Snow Cover Installation Position Diagram...
Page 15
NO.S009 Fixed Ladder Installation Position Diagram...
Page 17
NO.M004 Monitoring Device Installation Position Diagram Install the server onsite. Install ECC800 omnidirectional antennas and directional antennas onsite. Opening direction Slide 200mm Slide 200mm Opening direction Opening direction Slide 200mm UPS-2 UPS-1 Install the pad onsite. Air Conditioner-B1 Air Conditioner-C1 Fan-2 Air Conditioner-A1 Air Conditioner-D1...
Page 18
NO.S017 ECC800 3G/4G Antenna Installation Position Diagram ECC800 3G/4G antenna ECC800 3G/4G antenna Signal cable feeder window Ground...
Page 28
UPS Battery Cabinet-1 Guide Rail config Rack front Rack back Cable Manager Cabinet Tray Cabinet Tray Battery pack-12 L Type Guide Rail Battery pack-11 L Type Guide Rail Battery pack-10 L Type Guide Rail Battery pack-9 L Type Guide Rail Battery pack-8 Cable Manager L Type Guide Rail...
Page 29
NO.F004 Fire Extinguishing Device Installation Position Diagram (CE) EXIT EXIT-1 Opening direction Slide 200mm Slide 200mm Opening direction Opening direction Slide 200mm UPS-2 UPS-1 Connect cables for extinguishant control panel batteries onsite. Warning Signs-1 Abort Air Conditioner-B1 Air Conditioner-C1 Fan-2 Air Conditioner-A1 Air Conditioner-D1 (With Electric Heating &...
Page 30
NO.S012 External Camera Mounting Kit Installation Position Diagram External camera mounting kit Cable-routing Cable-routing board Cable-routing board Cable-routing board board External camera mounting kit Cable-routing board Cable-routing board Cable-routing board Cable-routing board Ground...
Page 31
NO.S014 Signal SPD Installation Position Diagram Signal SPD Cable-routing Cable-routing board Cable-routing board Cable-routing board board Signal SPD...
Page 32
NO.S016 Signal SPD Cable Routing Diagram Signal SPD ground point to DDF...
Page 33
Terminal Relation Table Container Window Terminal Spec From Terminal Spec From Cable NO. Container From Device Container To Device Breaker Huawei Part Description Huawei Part Code Part 1 Part 2 Part 1 Part 2 Provided by Provided by L1/L2/L3 Customer...
FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) 3 Removing Transport Protection Materials Removing Transport Protection Materials Table 3-1 Protection materials to be removed Device Protection Materials to Be Removed Smart cooling product Transport fastener for the compressor and liquid level...
Page 36
List of Initial Configuration Parameters Diagram Detailed Initial Configuration Category Diagram Name Parameters Power Supply and NO.P001 Distribution Device Layout Diagram Initial Configurations Power Supply and for the Power NO.P002 Distribution System Supply and Diagram Distribution Initial Configuration Initial Configuration Parameters for System an Integrated UPS Parameters for Power...
Page 37
Diagram Detailed Initial Configuration Category Diagram Name Parameters Monitoring Device Layout NO.M001 Diagram Initial Monitoring System Configurations NO.M002 Network Diagram for the Management Initial Configuration System Table 3 Parameters for the Management System Fire Extinguishing Device Initial NO.F001 Layout Diagram (CE) Configurations for the Fire Fire Extinguishing System...
Page 38
NO.P001 Power Supply and Distribution Device Layout Diagram UPS-2 UPS-1 Fan-2 Fan-1 Signal window Power window Power PDB-1...
Page 39
NO.P002 Power Supply and Distribution System Diagram Relay AC PDB-1 DC24V- DC24V+ AC PDB-1 PATH A PATH B IT Load 1 distribution Module IT Load 2 distribution Module IT Load 2 distribution Module IT Load 1 distribution Module Air Conditioner distribution Module Air Conditioner distribution Module BBB-1 MCB C32A/4P...
Page 40
Device Name Project Configuration Quantity Power Distribution Device Name Integrated UPS ■Involved □Not involved UPS-1/2 MCCB ■Involved □Not involved UPS-1/2 QF Note: The following device parameters are not all parameters of the devices. Only the parameters that need to be set for the project are listed. Default values will be used for the other parameters so they do not need to be set.
Page 41
Component UPS-1/2 Integrated UPS (25kVA-125kVA) Initial Configuration Parameters Category Parameter Default Value Value Range Setting Remarks 12 languages, including English, Chinese, Language English English Italian, and so on Basic Password 000001 Default value Single/Parallel Single Single, Parallel Single Output voltage level 400 V 380 V, 400 V, 415 V 380 V...
Page 42
Category Parameter Default Value Value Range Setting Remarks BCB connection Disable Disable/Enable Disable Dry Contacts Batter breaker Disable Disable/Enable Disable Battery Param. Installation time Set by service personnel User-defined (After setting the parameter to User- defined, disable the spare branch circuit breaker in PDU Parameters-PDU-Air conditioner- Enable Disable/Enable/User-defined...
Page 43
Component UPS-1/2 QF MCCB Current Parameter Settings 备 Category Parameter Default Value Value Range Setting Remarks 注 0000–1111 L overload protection (DIP switch setting) 1111 0(0.04)1(0.08)1(0.16)0(0.32) Step 0.04, can be set from 0.4 to 1 I protection (transient short circuit 0000–1111 Electronic MCCB current Step 0.5, can be set from 1 to 10...
Page 46
NO.C003 Indoor and Outdoor Unit Signal Cable Wiring Diagram UPS-2 UPS-1 Fan-2 Fan-1...
Page 47
Initial Configuration Parameters of Remote Temperature and Humidity Sensor DIP Switches for 25KW Air Cooled Precision Air Conditioners DIP Switch Sequence No. Sensor Name and No. Address Remote temperature and humidity sensor 1...
Page 48
Initial Teamwork Configuration Parameters for 25 Kw In-row Air Cooled Smart Cooling Product Teamwork Total Number of Cold Aisle Hot and Cold Aisle Teamwork Teamwork Forced Requirement Cascade Unit Network Number of Running Rotation Temperature Temperature and Conditioner Group No. Function Rotation Control...
Page 49
Initial Temperature and Humidity Configuration Parameters for 25KW Air Cooled Precision Air Conditioners Temperature and humidity Air Conditioner Cold aisle sensor 1 Temp control mode Cold-aisle temp set point Cold-aisle Humid Set Point control Air Conditioner-A1 Enable Cold aisle Average Air Conditioner-B1 Enable Cold aisle...
Page 50
Air conditioner pipe electric heater DLXELL XR02CX thermostat initial configuration parameters 备 Set Category Setting Item Default value Setting the threshold Factory Setting 注 Set Point -55 - 99 C14℃ 40℃ Differential 2.0°C 0.1 - 25 °C 5°C Anti-short cycle delay 0 - 50 min Adjusting Parameters Compressor ON time faulty probe...
Page 51
Extinguishant Control Panel electric heater DLXELL XR02CX thermostat initial configuration parameters 备 Set Category Setting Item Default value Setting the threshold Factory Setting 注 Set Point -55 - 99 ℃ 15℃ Differential 2.0°C 0.1 - 25 °C 5°C Anti-short cycle delay 0 - 50 min Adjusting Parameters Compressor ON time faulty probe...
Page 52
NO.M001 Monitoring Device Layout Diagram Opening direction Slide 200mm Slide 200mm Opening direction Opening direction Slide 200mm UPS-2 UPS-1 Air Conditioner-C1 Air Conditioner-B1 Fan-2 Air Conditioner-A1 Air Conditioner-D1 (With Electric Heating & (With Electric Heating & (25KW) (25KW) Fan-1 Humidifier 25KW) Humidifier 25KW) Power window Signal window...
Page 54
Table 3 Initial Configuration Parameters for the Management System WebUI User LCD User Port to Pre-fab. Monitoring Data Device Alarm Upper-Level Upper-Level Device Code Device Name Device Model Device IP Address Name and Name and Upper-Level Transfer Remarks Module Device Type Address Threshold...
Page 55
WebUI User LCD User Port to Pre-fab. Monitoring Data Device Alarm Upper-Level Upper-Level Device Code Device Name Device Model Device IP Address Name and Name and Upper-Level Transfer Remarks Module Device Type Address Threshold Device Device Port Password Password Device Port Smart ETH Collector_ECC800...
Page 56
NO.F001 Fire Extinguishing Device Layout Diagram (CE) EXIT-1 EXIT Opening direction Slide 200mm Slide 200mm Opening direction Opening direction Slide 200mm Warning Signs-1 Abort Air Conditioner-B1 Air Conditioner-C1 Fan-2 Air Conditioner-D1 Air Conditioner-A1 (With Electric Heating & (With Electric Heating & (25KW) (25KW) Fan-1...
Page 58
NO.F002 Fire Extinguishing System Conceptual Diagram (CE) - 2 L1 IN L1 IN L1 IN L1 IN L1 IN L1 OUT L1 OUT L1 OUT L1 OUT L1 OUT L1 OUT black black L1 IN L1 IN L1 IN L1 IN L1 IN L1 OUT L1 OUT...
Page 60
NO.F003 Emergency Exit Diagram Exit Opening direction Slide 200mm Slide 200mm Opening direction Opening direction Slide 200mm Air Conditioner-B1 Air Conditioner-C1 Fan-2 Air Conditioner-A1 Air Conditioner-D1 (With Electric Heating & (With Electric Heating & (25KW) (25KW) Fan-1 Humidifier 25KW) Humidifier 25KW) Signal window Power window Electric heating for air inlet window...
FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) A Common Torque Selection Table Common Torque Selection Table NO TE This table lists only the recommended torque for common screws, bolts, and pipe connectors. The torques you choose should meet project requirements.
Page 62
FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) A Common Torque Selection Table Item Tightening Torque (Tolerance: ±10%)/ (Unit: Kgf.cm) Cross Electric recessed screwdriv pan head thread forming screw Cross Pneumati recessed counters screwdriv unk head wood screw...
Page 63
FusionDC1000A Prefabricated Modular Data Center Quick Guide (2020, Argentina, YCRT) A Common Torque Selection Table Item Tightening Torque (Tolerance: ±10%)/ (Unit: Kgf.cm) ST4.8 Cross Pneumati 30 (for recessed checking, pan head screwdriv not for self- tightenin drilling tapping screw ST6.3...