2-10
4. Open the Vertical transport door.
5. Remove two Claws [3] and the Verti-
cal transport door [4].
6. Remove two Screws [5], and remove
the Jam processing cover [6].
7. Remove two Screws [7] and the Sep-
aration Roller 2 installation plate
Assy [8].
8. Using a soft cloth dampened with
alcohol, wipe the Separation Roller
[9].