If the AUDIX remained in the cabinet and the cabinet was not powered down:
6
At the AUDIX console, hold the Crtl key and type cc.
7
Type 5 at the prompt.
In about 2 minutes, the AUDIX boots up.
8
When the system initialization is complete, log in as craft.
NOTE:
If you have a dadmin login and password, you can use them instead of craft and the craft
password.
9
Check for AUDIX System errors.
Return to Task List

Resolve alarms [from R5/R6/R7/R8si]

Return to Task List
1
See your record of customer busy-outs and recreate the pre-upgrade busy-out states.
2
Type
display alarms
3
Examine the alarm log.
4
Resolve any alarms using the Maintenance for Avaya DEFINITY® Server SI (555-233-123) book.
Return to Task List

Run acceptance tests [from R5/R6/R7/R8si]

Return to Task List
Run any acceptance tests that are appropriate for this upgrade. The acceptance tests are listed in these 3
checklists:
Test single-carrier cabinet systems
Test multi-carrier cabinet systems
Test telephones and other equipment
For details of the tests, see
Test the System
Test Telephones and Other Equipment
SI Installation and Upgrades
June 2004
R5/R6/R7/R8si to Avaya Communication Manager
Task List: R5/R6/R7/R8si to Avaya Communication Manager
and press Enter.