Install the following equipment:
Original translation card in TN2401 circuit pack
TN2404 processor circuit pack
TN2401or TN2401/2400 Netcon/Paccon circuit pack
Return to Task List

Power up the system [from R5/R6/R7/R8si]

Return to Task List
CAUTION:
It may be necessary to reseat circuit packs. To prevent damage from static electricity,
always wear an Electromagnetic Compatibility (EMC) wrist strap (Comcode 900698226)
when handling all system components.
NOTE:
To prevent unnecessary trouble tickets, do not enable the system alarms (Alarm
Origination feature) until all installation and administration procedures are completed.
1
Power up the AC- or DC-powered system.
For Single Carrier Cabinets (SCC1)
System
Steps
AC
DC
The results of system tests display on the monitor.
2
Verify that all tests pass.
If any of the terminal messages indicate a test has failed or if the message
displayed, refer to Maintenance for Avaya DEFINITY® Server SI (555-233-123) to clear the
trouble.
Return to Task List
SI Installation and Upgrades
June 2004
a
Set the switch on the AC power panel to ON position (up).
b
Set the cabinet circuit breakers to ON.
This starts the system initialization and test. All red LEDs
on the circuit packs go on and then off.
a
At the DC Battery Cabinet (if installed), set the circuit
breaker to ON.
b
At the DC Power Cabinet, set the circuit breaker(s) on the
rectifiers to ON.
This starts the system initialization and test. Some red
LEDs may be turned on, but they are turned off during the
boot-up process. No action is required.
R5/R6/R7/R8si to Avaya Communication Manager
Task List: R5/R6/R7/R8si to Avaya Communication Manager
is
spe down mode
121

Advertisement

Table of Contents
loading

This manual is also suitable for:

Scc1

Table of Contents