Power up [from G3V4]

Return to Task List
Set the circuit breaker to ON.
CAUTION:
It may be necessary to reseat circuit packs. To prevent damage from static electricity,
always wear an Electromagnetic Compatibility (EMC) wrist strap (Comcode 900698226)
when handling all system components.
NOTE:
To prevent unnecessary trouble tickets, do not enable the system alarms (Alarm
Origination feature) until all installation and administration procedures are completed.
1
Power up the AC- or DC-powered system.
For Single Carrier Cabinets (SCC1)
System
Steps
AC
DC
The results of system tests display on the monitor.
2
Verify that all tests pass.
If any of the terminal messages indicate a test has failed or if the message
displayed, refer to Maintenance for Avaya DEFINITY® Server SI (555-233-123) to clear the
trouble.
Return to Task List
82
a
Set the switch on the AC power panel to ON position (up).
b
Set the cabinet circuit breakers to ON.
This starts the system initialization and test. All red LEDs
on the circuit packs go on and then off.
a
At the DC Battery Cabinet (if installed), set the circuit
breaker to ON.
b
At the DC Power Cabinet, set the circuit breaker(s) on the
rectifiers to ON.
This starts the system initialization and test. Some red
LEDs may be turned on, but they are turned off during the
boot-up process. No action is required.
spe down mode
SI Installation and Upgrades
June 2004
is

Advertisement

Table of Contents
loading

This manual is also suitable for:

Scc1

Table of Contents