2.1 Before installation

Make sure to acknowledge and follow the local and national requirements on installation and the use of high voltage
units.
Before installation, check the contents of the packages and make sure the parts are not damaged.
Before you remove the power source completely from its packaging, install the wheel set.
Before you install the power source on the site, see the following requirements regarding the mains cable type and fuse
rating.
The mains cable must be installed by an authorized electrician.
Provided that the public low voltage short circuit power at the point of common coupling is higher than or equal to
5.1 MVA, this equipment is compliant with IEC 61000-3-11 and IEC 61000-3-12 and can be connected to public low
voltage systems. It is the responsibility of the installer or user of the equipment to ensure, by consultation with the dis-
tribution network operator if necessary, that the system impedance complies with the impedance restrictions.
Cable type and fuse rating requirements:
UNIT AMPERAGE
400 A
500 A
600 A
© Kemppi
HIGH VOLTAGE VERSION (380-460V)
CABLE TYPE
FUSE RATING
2
6 mm
25 A
2
6 mm
32 A
2
6 mm
35 A
MULTI-VOLTAGE VERSION (220-230/380-460V)
CABLE TYPE
-
2
16 mm
2
16 mm
22
X8 MIG Welder
Operating manual - EN
FUSE RATING
-
63 A
63 A