9 Maintenance

9.1 Maintenance schedule

This section covers maintenance of both FlexLoader SC 6000 and options that are
not included in all installations. If the installation contains further parts, maintenance
instructions may also be found in other documentation.
FlexLoader SC 6000 is made of components that have a minimal maintenance
requirement. However, there are some components that require scheduled
maintenance.
Always make sure that FlexLoader SC 6000 is turned off during maintenance.
Below is an overview of the maintenance intervals and the corresponding corrective
actions.
Maintenance intervals
Daily
Every week
Every month
Every 3 months
Every 6 months
When necessary
If the system has been
changed
Automatic
After 10 million cycles.
Product manual - FlexLoader SC 6000
3HAC051768-001 Revision: D
WARNING
Always follow the general safety instructions, see
© Copyright 2014-2020 ABB. All rights reserved.
Corrective action
Clean the conveyor belt.
Check the conveyor belt.
FlexLoader SC 6000 overall cleaning.
Clean the air cleaning box (option).
Check the oil level of the compressed air lubricator (option).
Check the electrical functions.
Check the gripper system.
Clean marking unit stylus pin guide and assembly.
Check the safety functions.
Check the cables and the cable rack.
Check the connections.
Replace the compressed air filter cartridge
Adjust the conveyor belt.
Replace the illumination tower lamps.
Check, clean and replace the sensors and sensor reflectors.
Clean the camera optics.
Clean the PC screen.
Drain the air preparation condensate
Backup the robot program.
Backup the vision system.
Create recovery image of vision PC.
Windows updates (performed as long as PC has internet con-
nectivity)
Lubricate the gripper system.
9 Maintenance
9.1 Maintenance schedule
Safety on page
13.