8 Operation

8.1 Overview

During operation, the FlexLoader SC 6000 operator workstation is located where
new material is added. During teachin, the operator workstation is located at the
FlexLoader Vision monitor.
Product manual - FlexLoader SC 6000
3HAC051768-001 Revision: D
WARNING
FlexLoader SC 6000 may only be operated by trained operators with the required
knowledge of the functions and risks related to FlexLoader SC 6000.
DANGER
Before FlexLoader SC 6000 is started or restarted, always check that all safety
devices are working properly and that no damage can be caused at startup.
DANGER
Make sure that the air pressure to the gripper is safely shut down before replacing
or repositioning the gripping fingers.