GALaxy eHydro Elevator Controller
3.2

Start-Up Procedures

3.2.1 Requirements for a running platform during initial startup

1)
Wire Hydraulic Pumping Unit and Main Line Power as shown in the job connection diagrams.
2)
If elevator requires a Governor, install and wire the Governor as shown in the job connection
diagrams.
3)
Add temporary connections on the GALX-1121 Main I/O Board and on the I/O expansion boards
as shown in Figures 1, 2, and 3.
4)
Set the toggle switches on the Main I/O Board as shown in Figure 3.
Place CN18 on pins 2 and 3, in the temporary "Test Mode" configuration, on the GALX-1121 Main
5)
I/O Board, as shown in Figure 3.
All temporary connections must be removed before placing the elevator in service.
Figure 3-0: Typical I/O Expansion Board
Fire I/O Board
Section 3 – GALaxy Startup and Adjustment
Figure 3-1: GALX-1121 Main I/O Board With
Run Bug. See Figure 3-2 For
Run Bug Stop Switch.
3-2