4 Individual remote controls
PC-ARF

4.1.2.5 Installation space

In case of installing the controllers in vertical line, keep a distance more than 50mm
between the controllers vertically.
If the distance is insufficient, the controller can not be taken out.

4.1.2.6 Installation procedure

1 Insert the edge of the slotted screwdriver into the groove at the bottom of the holding bracket, push and turn the slotted
screw driver and then remove the remote control switch from the holding bracket.
Groove part
Groove Part
2 Attach the remote control switch to the holding bracket and connect the cable as follows:

In Case of Exposing Remote Control Cable
a. Fix the holding bracket onto the wall with screws (accessory).
b. Attach the stopper (plastic band) to the cable at the inside of the draw-out hole.
Cable
Band stopper
(Field-supplied)
63
TCGB0106 rev.0 - 12/2014
Approx. 6mm
Slotted
Screw driver
Figure seen from bottom side
Draw-out hole
Lead the cable with its sheath peeled through the groove.
Lead the cable with its
sheath peeled through
the groove.
Peel the insulation at the end of the cable and clamp
Peel the insulation at
the M3 solderless terminals (field-supplied).
the end of the cable and
clamp the M3 solderless
terminals (field-supplied).
Rear cover
Groove for attaching
controller
> 50mm
4