16. For each threaded rod, finger-tighten the 5/8 inch nut and washers against the bottom of the
Figure 38: Anchoring on Raised Floor Over Concrete Slab
floor tile (see
Note: Tighten only until the washers and nuts are flush with the bottom of the floor tile. DO
NOT over tighten, causing the tile or frame to tilt.
17. With a 3/4 inch (19mm) socket wrench, tighten each torque nut inside the frame until the twist
off nut above the plastic red cover breaks free.
Leave the twist off nut on the threaded rod to indicate that the torque on the nut beneath has
been set properly.
18. If any tiles were removed to access the underside of the raised floor, replace them.
19. This procedure is complete.
Next, go to
How to Anchor to Overhead Rack of HD Frame
How to Anchor on Raised Floor Using Support Channel
Use the following procedure to an
assembly shown in

Figure 39: Anchor Assembly for Use with Support Channel

1. Ensure that
Additional Preparations for Raised Floors
2. For each threaded rod, thread the following components in the order shown onto one end of
the rod (these components are threaded on the rod while the rod is upside down; see
910-2969-001 Revision K, June 2009
chor the HD frame to the raised floor tiles using the anchor
Figure 39: Anchor Assembly for Use with Support Channel
How to Install aT1100 AS Frame
on page 61).
on page 66.
on page 63.
on page 56 has already been performed.